Project Title : Karimi & Ferdowsi Interchanges (EPC)

Location : Iran - Qom
Status : Completed - Road
Start Date : 2014 End Date : 2016
Technical Specifications :

Length of project: 2,344 m

Underpass bridges: 14 No.

Length of Retaining walls: 1,890 m

Earth works: 977,000 m3

Pile Drilling: 16,450 ml

Steel works: 6,500 ton

Formworks: 125,000 m2

Concrete: 65,100 m3

Guardrail & handrail: 867,000 kg

Sub base: 63,000 m3

Base: 43,000 m3

Asphalt: 750 ton

Employer

Ministry of Roads and Urban

Engineer

Hexa Consulting Engineers

Updated Contract Price

32,000,000 USD


 

Description :

This project which is located at Qom province, is involved two interchanges between Payambar-e-Azam Highway and Karimi Street and also between Payambar-e-Azam Highway and Ferdowsi Street and consists of excavation & earth filling works in soil and rocks, drilling and execution of piles, construction of underpass bridges, retaining walls, and asphaltic pavement.