Project Title : Saveh Hydro-power Station & Irrigation System - Turn Key
|
|
Location : Iran - Markazi |
Status : Completed - Hydro-power Station |
Start Date : 1991 | End Date : 1995 |
Technical Specifications : Station output: 5 MW tunnel of Water transmission tunnel with 4 m diameter: 410 m Length of canal: 9.5 km Earth works: 1,000,000 m3 Concrete: 45,000 m3 Steel works: 3,100 ton |
Employer Tehran Regional Water Authority Engineer Moshanir Consulting Engineers Updated Contract Price 20,500,000 USD
|
Description :
This project located at the west of Saveh, near Asiabak village. The hydro-power station is a complementary part of Saveh dam, in order to reserve the output of the dam for irrigation purpose. |
|